Supreme Court: Contractor’s Collapse Does Not Cancel Compensation for Delay in Delivering the Apartment

The Supreme Court of Israel granted the appeal of apartment purchasers in a building reinforcement project in Bat Yam. The Court held that if the financing companies decided, through the receiver, to complete the project on the basis of the existing sale agreements, they could not demand full payment while at the same time disregarding the provision concerning compensation for delay.

Key facts

  • •Case: CA 3301/23
  • •Court: Supreme Court of Israel
  • •Appointment of receiver: January 2021
  • •Legal costs: 25,000 shekels
  • •Applicable law: Sale (Apartments) Law
  • •Source publication date: October 18, 2026

The Apartment Was Not Delivered

The contracting company received the right to build 14 new apartments in exchange for reinforcing the existing building. The appellants purchased one of them: the apartment was to be delivered within 24 months from the date the building permit was obtained, which was issued in December 2017. The agreement provided for compensation for a delay exceeding 60 days, in accordance with the Sale (Apartments) Law.

The Receiver Continued the Project

After the contractor failed to repay the loans, a receiver was appointed in January 2021. Two financing companies decided to complete the construction through the receiver in accordance with the existing sale agreements. The other purchasers received their apartments no later than April 2025, but the appellants’ apartment had not yet been delivered as of the source’s publication date because of the legal proceedings.

The Agreement Cannot Be Performed Selectively

Justice Ruth Ronnen, with the concurrence of Deputy President of the Supreme Court Noam Sohlberg and Justice Yael Willner, held that the sale agreement remained fully applicable. Although the proceeding was formally presented as the enforcement of liens, the nature of the security and the decision to complete the project required the application of insolvency law. Accordingly, the receiver must take into account the interests of all creditors, including the apartment purchasers.

Priority Depends on the Period of Delay

Compensation for the delay up to the receiver’s appointment will be paid only after the debts to the financing companies have been repaid. By contrast, the claim for the period following the appointment has priority over their debt, and the purchasers may set off that amount against the balance of the apartment’s purchase price. The case was remanded to the District Court, which must determine the purchasers’ entitlement to compensation and calculate its precise amount; the respondents were also ordered to pay them legal costs of 25,000 shekels.

What this means for you

The contractor’s bankruptcy or financial collapse does not in itself cancel the purchaser’s contractual right to compensation for delay. If the financing party decides to complete the project in accordance with the existing agreements, it cannot rely only on the terms that benefit it. However, payment priority depends on whether the delay arose before or after the receiver’s appointment.